Stadiu Lucrari August


  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August
  • Stadiu Lucrari August

Structura de rezistenta
– rampa acces subsoluri – 90 %

Compartimentari exterioare si interioare
– zidarie – 100 %

Instalatii electrice
– electrice etaj mezanin – 25 %
– electrice etaj etaj 1 – 100 %

Instalatii sanitare
– subsoluri – 60 %
– retele exterioare – 90 %

Instalatie gaz – 70 %

Tencuieli
– etaj mezanin – 0 %
– etaj 1 – 70 %
– casa scarii – 100 %

Incalzire pardoseala
-etaj 1 – 20 %
– etaj 9 – 100 %

Sape
– etaj 9 – 100 %

Perete cortina parter – 80 %

Fatade – placare polistiren si decorativa
Fatada EST – 100 %
Fatada SUD – 100 %
Fatada Nord – 100 %
Fatada Vest – 30 %

Fatade – placare piatra
– Fatada Est – 90 %

Balustrade
Fatada Est – 100 %
Fatada Nord – 100 %
Fatada Vest – 100 %

Montaj Alucobond balcoane
Fatada Est – 30 %

Hidroizolatii
Terasa necirculabila etaj tehnic – 100 %
Terasa etaj retras – 100 %

Glet
– Etaj 6 – 100 %
– Etaj 7 – 100 %
– Etaj 8 – 60 %
– Etaj 9 – 100 %

Stadiu lucrari august


  • Stadiu lucrari august
  • Stadiu lucrari august
  • Stadiu lucrari august
  • Stadiu lucrari august
  • Stadiu lucrari august
  • Stadiu lucrari august
  • Stadiu lucrari august

Structura:

Corp secundar C3 este gata in proportie de 100%
finalizata placa peste etajul 2
turnat stalpi si diafragme etaj 3
turnat placa peste etaj 3
turnat stalpi si diafragme etaj 4
turnat placa peste etaj 4 in proportie de 50%
turnat stalpi si diafragme etaj 5 in proportie de 50%
finalizat hidroizolatiile pe exterior la fundatii in proportie de 90%
executare zidarie de inchidere in proportie de 20% etaj 1